Troubleshooting Case Study

Troubleshooting Case Study

Pinewood Studios

Pinewood Studios is one of the world's leading destinations for the makers of film, television and commercials.

Following a detailed site survey together with analysis of billing data, we produced a comprehensive report on energy use at the site.  It revealed major energy saving potential in terms of running-costs and carbon savings.

The challenge was to then produce a list of priorities and offer accurate and realistic capital cost budgets to allow paybacks to be assessed.   A priority schedule of works could then be finalised.

The primary recommendations included strategies and then detailed design, for decentralisation of the buildings sited at the extremes of the existing inefficient district heating scheme.  This involved the installation of new gas fired boilers into an existing basement plant room and the strip out of existing “pre-historic” boilers (shown in the picture).

The challenging elements here included connection to the old large bore heating systems and the issues caused by the years of dirt build up within the existing system. Also working with the limited plant room space and the installation of new flues in existing chimneys.

The first-phase works also included the strip out of 10 old fashioned  heavy weight calorifiers and their replacement with electric immersions. The central system can now be shutdown during the summer and together with the introduction of motorised zone valves onto the distribution has given a much higher level of control.

The introduction of a new small base load boiler on the 9MW central plant improved efficiency of operation during low load conditions.

The works required careful phasing as all the buildings remained operational throughout and connection onto old systems had to be managed with no record information. An additional challenge involved the removal of the heavyweight existing equipment. 

As the first phase of works is completed, the next level of implementation which includes more basic items such as TRV’s, insulation works and introduction of variable speed drives will come online.

More Case Studies
Renewable Energy - "Merlewood", Cumbria

“Merlewood” close to Grange-Over-Sands in Cumbria is a Lakeland home of the Holiday Property Bond. The first phase which became operational in May 2011, involved the conversion of the house into 9 apartments and a leisure centre.  The second phase comprises of 46 new build apartments which are due for completion in the summer of 2012.

The site is served by a 500 KW biomass boiler.  Woodchip is sourced locally and delivered from a local depot.   The boiler is fed via a leaf spring /auger system from the adjacent chip store.   The chip store is positioned within the landscape to allow delivery vehicles to tip directly into the store via a simple key switch powered lid.

more

3D Modelling - Canizarro Hotel, Wimbledon

This 300 year old 4 star boutique hotel in Wimbledon has 46 individually designed bedrooms. In order to create more internal dining space and to maximise the view out onto the garden area, it was proposed to enclose an existing ornate portico adjacent to the dining room, with a glazed façade and to provide heating to the space.

Building Control requirements were that the CO2 emissions from the building as a whole would not be increased by the new high performance glazed facade. In order to demonstrate this, the whole building was surveyed, the plant and system information gathered and a 3D building model was created for both the existing arrangement and the proposed enclosed portico arrangement.

more

 

The White Cottage, 6 Station Road, Loudwater, Bucks, HP10 9TZ : 01494 471240